The Trans Mountain expansion project would triple the capacity of the existing pipeline between Edmonton and a shipping terminal in Burnaby, B.C. (Canadian Press file images)

Trans Mountain pipeline expansion cost jumps 70% to $12.6 billion

The estimate of $7.4 billion was made in 2017 by the previous owner

The cost to build the Trans Mountain pipeline expansion has jumped by 70 per cent to $12.6 billion from a three-year-old estimate of $7.4 billion.

President and CEO Ian Anderson says the company owned by the federal government has spent $2.5 billion to date, including the impact of delays and additional regulatory processes, leaving an additional $8.4 billion needed to complete the project, plus $1.7 billion of financial carrying costs.

He says the project is now expected to be in service by December 2022.

The estimate of $7.4 billion was made in 2017 by the previous owner, Houston-based Kinder Morgan, Inc., which sold the expansion project and the existing pipeline to the federal government in 2018 for $4.5 billion.

Opponents have attacked the greenhouse gas emission and oil spill risks of the pipeline project but they’ve also charged it will be a money-loser with unproved markets in Asia that will fail financially and leave the public holding the bag.

ALSO READ: Opponents in B.C. to ramp up protests against Trans Mountain pipeline

Anderson says the company is recommending that Ottawa, as owner and lender, set aside a further $600 million reserve for cost impacts beyond the control of Trans Mountain.

Opponents of the pipeline expansion have vowed to do whatever it takes to stop the project despite losing a legal challenge before the Federal Court of Appeal earlier this week.

The four First Nations who lost the court challenge on Tuesday have 60 days to seek leave to appeal to the Supreme Court of Canada.

The expansion project would triple the capacity of the existing pipeline between Edmonton and a shipping terminal in Burnaby, B.C.

The Canadian Press

Like us on Facebook and follow us on Twitter.

Trans Mountain pipeline

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Penticton Vees recognized on and off ice success

The awards were given out following their Saturday night win.

Dale family was prominent in Summerland’s past

Ruth Dale taught for many years

Penticton Vees comeback for overtime win to end regular season

The Vees were down 3-0 to start the third before putting together an epic comeback.

PHOTOS: Celebrating diversity in Penticton

Seventh annual OneWorld Festival celebrates the worlds of different cultures in the South Okanagan.

Fiery collision involving truck closes Highway 1 at Three Valley Gap

Drivers should expect major delays and congestion; estimated time of re-opening is 2 p.m.

VIDEO: 2020 BC Winter Games wrap up in Fort St. John as torch passes to Maple Ridge

More than 1,000 athletes competed in the 2020 BC Winter Games

Still six cases of COVID-19 in B.C. despite reports of Air Canada passenger: ministry

Health ministry wouldn’t comment on specific flight routes

Violent ends to past Indigenous protests haunt Trudeau government

Trudeau adopted a more assertive tone Friday, insisting the barricade must come down

Kelowna Firefighters douse suspicious hedge fire

A 30’ section of cedar hedge burned prompting an RCMP investigation.

Kelowna RCMP make arrest in fatal stabbing of 16-year-old Elijah Beauregard

An 18-year-old woman is in police custody facing a manslughter charge.

HIGHLIGHTS: Day one and two at the 2020 BC Winter Games

Athletes had sunny – but cold – weather to work with in Fort St. John

B.C. money laundering inquiry to begin amid hopes for answers, accountability

Eby argued that most B.C. residents already know the previous government, at best, turned a blind eye

Most Read