B.C. issues Trans Mountain pipeline permit update as premier heads to Ottawa

Ministry says 201 of 587 permit applications submitted to various permitting agencies are approved

B.C.’s government has issued a progress report on permits for the Trans Mountain pipeline expansion, just as Premier John Horgan readies to travel to Ottawa for a meeting on the controversial project.

The Energy, Mines and Petroleum Resources Ministry says the $7.4-billion project requires 1,187 provincial permits, many of which involve Indigenous consultations.

The ministry says in a statement that 587 permit applications have been submitted to various permitting agencies and of those, 201 have been approved and issued while another 386 are under review.

The report comes as Horgan denies that B.C. is delaying the permitting process, but his statements haven’t satisfied Alberta, the federal government or Kinder Morgan, the pipeline’s owner.

The company announced last week it is stopping essential spending on the project because of opposition and delays in British Columbia and it gave May 31 as a deadline for government action.

Prime Minister Justin Trudeau has summoned Horgan and Alberta Premier Rachel Notley to Ottawa for a meeting on Sunday to discuss the escalating pipeline feud.

READ MORE: ‘I dare you’: B.C. councillor calls out feds in pipeline dispute

READ MORE: B.C. blasted for Trans Mountain pipeline tactics

READ MORE: Oil-by-rail traffic rises as B.C. battles over Trans Mountain pipeline

Notley said this week Alberta is preparing to punish B.C. with legislation that could restrict the flow of oil to the West Coast, likely causing a spike in gasoline prices, which currently hover around $1.50 a litre in Metro Vancouver.

Notley also said Alberta is prepared to take over the pipeline.

The federal government approved the project, which would triple capacity of the pipeline running between Edmonton and Burnaby in 2016.

Trudeau has repeatedly said Trans Mountain is in the national interest and will get built.

B.C.’s Energy, Mines and Petroleum Resources Ministry said in a statement Friday that Kinder Morgan must still submit about 600 permits for the expansion.

It said the submitted permits must align with 37 conditions outlined in B.C.’s environmental certificate and the 157 conditions detailed in the National Energy Board’s approval.

Horgan said Friday that B.C. is heading to court to test its jurisdictional authority over the pipeline, but until then, the government is not holding up the expansion.

“We are not thwarting the project,” he said. “We are issuing permits as they ask for them.”

But the provincial government will continue to state its belief that the pipeline poses environmental and economic risks that are too great, Horgan added.

“I do believe we have a mandate to defend the coast,” he said. “I would also argue the premier of B.C. has an obligation at all times to stand up for the jurisdictional authority of provincial rights.”

The Canadian Press

Like us on Facebook and follow us on Twitter.

Just Posted

Summerland Museum asks for World War I artifacts

Upcoming exhibit will examine end of war and effects on Summerland soldiers

Canadian concert series returns to Oliver winery

Tinhorn Creek Vineyards announced the return of its Canadian Concert Series for 2018

Cleaning up the highway

Members of Summerland’s Bottleneck Drive picked up garbage along Highway 97 in Trout Creek.

Summerland students to hold fair trade fair

One-day event will be held on May 27 in Memorial Park

‘N’ driver in McLaren caught going 70 km/hr in playground zone

Vancouver police said the driver was fined $368 and the luxury car impounded for seven days

Dr. LipJob ordered to stop doing botox and other medical procedures

Rajdeep Kaur Khakh ordered to stop unlawful practice of medicine

B.C. to prevent for-profit blood, plasma collection

Voluntary Blood Donations Act would make it illegal to pay for blood, plasma donations

Fire destroys historic house at Hilltop Gardens near Spences Bridge

Spences Bridge firefighters responded to the blaze, but were unable to save the house

Bill Cosby guilty in sexual assault case

Comedian convicted of drugging and molesting a woman

B.C. legislates recreational marijuana sales

Age limit 19, province retains wholesale cannabis monopoly

COLUMN: Stanley Cup playoff second-round predictions

Sidney Crosby and the Penguins continue their quest for their third straight Stanley Cup

B.C. seeks court ruling on new pipeline regulations

Province wants to require permits for any new bitumen transport

Most Read